Today, 6 October, a public consultation is being held at Lagan Valley LeisurePlex on proposals for a substantial new Holiday Park on Ballyskeagh Road, Drumbeg, within the Lagan Valley Regional Park Area of Outstanding Natural Beauty.
The proposal is not insignificant.
The consultation material published today reveals a 6.4-hectare development including 17 holiday accommodation units, 11 camping-pitch units, four padel courts, two lakes, a reception and convenience building, roads, parking and almost 1.4km of walking trails. Some of the proposed two-storey holiday buildings would be approximately nine metres high.
You might therefore imagine that a public consultation about a development of this scale, in one of Northern Ireland’s most sensitive landscapes, would be difficult to miss.
We have found the opposite.
We went looking
This morning, on the day of the consultation, Quarterlands searched for public information advertising the meeting.
We searched Google using the planning reference LA05/2026/0608/PAN, Ballyskeagh Road, the Holiday Park, Gill Hall, Bell Rolston and Lagan Valley LeisurePlex.
We checked the Planning Portal.
We searched for Belfast Telegraph coverage.
We checked Bell Rolston’s website.
The Planning Portal confirms the PAN and the location of the proposed development, but this morning contained only four documents relating to the PAN, principally the application paperwork and site location plan. Independent planning indexes similarly record the PAN as received on 24 July and determined as acceptable on 28 September.
What appeared prominently in Google searches advertising today’s actual event?
Rather awkwardly, Quarterlands did.
Our own article, A Holiday Village in Drumbeg? Public Meeting – Please Come Along, published on 30 September, was appearing prominently in searches for the consultation. It gives the date, venue and planning reference and asks people to attend.
We also found Facebook posts from local elected representatives which had shared details of the proposed consultation.
What we have not yet been able to find through online searches is the applicant’s newspaper advertisement for today’s public event.
That matters.
What the law requires
This is not simply a developer choosing to hold an informal exhibition.
The consultation forms part of the statutory Pre-Application Community Consultation (PACC) process for a major planning application.
Section 27 of the Planning Act (Northern Ireland) 2011 requires a prospective applicant for major development to submit a Proposal of Application Notice before submitting the eventual planning application. At least 12 weeks must then elapse before that application can be submitted.
The detailed consultation requirements are contained in the Planning (Development Management) Regulations (Northern Ireland) 2015.
The statutory minimum includes at least one public event at which members of the public can comment on the proposed development.
Importantly, details of the proposal and consultation must also be published in a local newspaper at least seven days before that event.
The required advertisement is not supposed to be vague. Guidance on the statutory process says it should include the location and description of the development, where further information can be obtained, the date and location of the event, how and by when comments can be submitted, and clarification that comments made at this stage are being made to the prospective applicant rather than the planning authority.
There has also been an important recent change.
The Planning (Miscellaneous Amendments) Regulations (Northern Ireland) 2025 added a requirement for the prospective applicant to maintain a website displaying details of the proposed development and allowing members of the public to comment. Those details must be displayed for a minimum of 28 days during the statutory consultation period and after publication of the newspaper notice.
Bell Rolston’s consultation website is now live. It states that the consultation runs from 6 October to 3 November and the detailed ten-page consultation brochure became available online today.
The brochure itself confirms that comments may be submitted until 3 November and directs the public to Bell Rolston’s website to view the information and provide feedback.
That satisfies an important purpose: people who cannot attend today’s three-hour event still have an opportunity to examine the proposal and respond.
But it raises another question.
Why was the detailed information only published on the day of the meeting?
A letter from Bell Rolston dated 22 September, received by one local resident and subsequently shared with Quarterlands, gave notice of today’s event.
It also stated that the proposal information would be available on the Bell Rolston website from 6 October until 3 November.
In other words, the detailed consultation boards describing the scale and design of the proposed development became publicly available online on the same day as the public event.
Someone wishing to attend today’s meeting informed and prepared therefore had only a matter of hours to study material revealing, among other things, two-storey holiday buildings approximately nine metres high, two lakes, four padel courts, internal roads and parking, part of the site within the fluvial floodplain, and a series of environmental assessments which have not yet been completed or published.
We think it is reasonable to ask whether meaningful community consultation would have been better served by making this information available before the public event.
And where is the newspaper advertisement?
This is the question we are now trying to establish.
Information shared publicly in July indicated that the consultation was expected to be advertised in the Belfast Telegraph on 22 September.
We have searched for that advertisement online today and have not found it.
That does not mean that the required advertisement was not published. A print advertisement may not be indexed by Google or available through an ordinary search of the newspaper’s website.
So we are not claiming that the statutory newspaper advertising requirement was breached.
We are asking a much simpler question:
Where was the public event advertised, when was it advertised, and how easily could an ordinary member of the public have discovered that it was taking place?
That should be straightforward to establish.
When the eventual planning application is submitted, it must be accompanied by a Pre-Application Community Consultation Report explaining what consultation took place and how comments received were considered. Guidance on PACC reports expects evidence of consultation, including dates and copies of advertisements and information about the public events held.
So there should ultimately be a documentary trail.
Consultation requires people to know there is a consultation
Quarterlands only learned of the detailed arrangements because information was shared with us.
Once we had it, we circulated it widely. We contacted councillors, MLAs, MPs, environmental and community organisations and many of the groups and individuals who have contacted Quarterlands over the years. We published the meeting on our website and produced a leaflet for people to share.
That was our choice as a community group.
It should not, however, be confused with publicity undertaken by the prospective applicant as part of the statutory consultation process.
The purpose of pre-application community consultation is surely more than the existence of a meeting somewhere on a particular afternoon. It is to give the community a genuine opportunity to know what is proposed, understand it, ask questions and respond before important decisions become embedded in a final planning application.
The legislation provides mechanisms intended to make that happen: a public event, advance newspaper advertising, online information and a consultation period.
Today we will be attending primarily to listen.
We want to establish what studies have been undertaken, what remains to be done, what is proposed for sewage and drainage, how flooding has been considered, what ecological surveys have been carried out, how the development will be lit and operated, and how buildings of this scale are intended to sit within the Lagan Valley AONB.
And we will ask one additional, very simple question:
How was the wider public notified about today’s consultation, and why was the detailed consultation material only made publicly available online on 6 October, the same day as the consultation event?
The consultation remains open until 3 November 2026.
There is time to ask questions.
And we intend to.